North Abingdon development Latest News
From next Monday 8th June, in addition to the north bound Lodge Hill A34 slip closure, David Wilson Homes commence 4 weeks of 4-way traffic lights at the Peachcroft Roundabout as Phase 2 of the works between them and Bellway to deliver the overall road infrastructure for North Abingdon.
RPG, the northern sites promoter and land lead, have set up a website to give information on these projects plus the District Centre part of the developments.
The web link is below:-
Key points:
On the Home Page it covers who is doing what and the working hours for David Wilson have now been confirmed as 07:00 to 20:00, although not yet how many days a week.
On the FAQs page at point 4, there is a link to click to ask questions. This opens an email window pre-addressed to Victoria Walker at RPG, who will deal with it. Victoria has put the website together and will be responsible for chasing and collating the developer updates every fortnight.
Once David Wilson get final confirmation from County Highways on their road space request, a planner will be added.
Bellway appear to have completed their Phase 1 2 weeks of traffic light-controlled works early, so the Twelve Acre Drive progress has been in line with programmed dates.